Mumbai's first large-scale waste-to-energy plant 93% complete, trials in Dec
<img border="0" hspace="10" align="left" style="margin-top:3px;margin-right:5px;" src="https://timesofindia.indiatimes.com/photo/136209732.cms
Mumbai's first large-scale waste-to-energy plant at Deonar is nearing completion and will begin trial runs in December. The project is 93% complete and expected to generate electricity by early 2027. Issues with logistics and statutory clearances have contributed to delays in its original timeline. The plant will process fresh municipal waste and generate up to 8 megawatts of electricity d